Property reference

com.snc.project.rollup_project_start_date

The com.snc.project.rollup_project_start_date property determines whether the planned start date of a project is derived from the earliest task's planned start date. Admins should care about this setting to ensure project timelines accurately reflect task schedules.

Default: true Type: boolean Application: Global

Key questions about this property

The answers below summarize the purpose, scope, default effect, and review scenarios for this property.

What does it do? When enabled, this property rolls up the planned start date of a project from the earliest task's planned start date, ensuring alignment between tasks and the overall project schedule.
What area does it affect? Project Management
What does the default mean? The default value is "true", which means this behavior is enabled by default.
When should you review it? Review this property when adjusting project timelines or task schedules.

Out of the box property record

Raw metadata from the property record.

Property name com.snc.project.rollup_project_start_date
Sys ID b300f0623720020033cb26877e41f16b
Type boolean
Application Global
Default value true
Description Rollup project start date from tasks
Updated 2017-07-16 23:49:08

Sources

Official references and nearby text excerpts where this property appears.

Documentation excerpt View supporting context
Context preview Snippet 1
... true, this property updates the cost of a parent project task if the cost of the child task is updated. Default value: false Roll up project start date from tasks com.snc.project.rollup_project_start_date If set to true, the project planned start date rolls up from the planned start date of the earliest task. Disable this property if you want the project planned start ...