Property reference

com.snc.resource_management.do_not_allow_resource_plan_dates_outside_project_demand_dates

This property prevents resource plan dates from being set outside the defined project or demand dates. Admins should consider enabling this setting to ensure resource planning aligns with project timelines and avoids scheduling conflicts.

Default: false Type: boolean Application: Global

Key questions about this property

The answers below summarize the purpose, scope, default effect, and review scenarios for this property.

What does it do? It restricts the ability to set resource plan dates beyond the project's demand dates, ensuring consistency in project scheduling.
What area does it affect? Resource Management
What does the default mean? The default value is "false", which means this behavior is disabled by default.
When should you review it? Review this property when configuring resource planning processes or adjusting project timelines.

Out of the box property record

Raw metadata from the property record.

Property name com.snc.resource_management.do_not_allow_resource_plan_dates_outside_project_demand_dates
Sys ID 67ccd83f53e120104196ddeeff7b12dd
Type boolean
Application Global
Default value false
Description Do not allow resource plan dates to be outside the project/demand dates
Updated 2021-01-20 08:00:34

Sources

Official references and nearby text excerpts where this property appears.